Free construction BOQ template for Excel

This free Excel workbook gives you a clean starting point for a construction BOQ. It includes a main pricing sheet, a rate build-up sheet and notes on how to use both. The template contains formulas but no market rates, so your team can enter current project-specific quantities, quotations and commercial allowances.

Free Excel workbook

Get the construction BOQ pricing template

Three sheets: BOQ Pricing, Rate Build-Up and Instructions. Formulas are included. Rates and quantities are blank.

We use these details to provide the resource and understand who finds it useful. Marketing is optional. Read our Privacy Policy.

What is inside the workbook?

SheetPurposeUseful fields
BOQ PricingPrice the measured work and calculate line amountsDescription, unit, quantity, tender rate, amount, source and assumptions
Rate Build-UpShow how the cost and tender rate were formedMaterial, labour, plant, subcontract, other cost, waste, overhead and markup
InstructionsExplain the formulas and a safe review workflowSetup, document control, quote checks and submission review

How to use the template

  1. Save a working copy with the project name, tender reference and revision.
  2. Copy the issued BOQ lines into the pricing sheet without changing the source file.
  3. Enter quantities and rates only after checking the applicable documents.
  4. Use the rate build-up sheet for items that need resource-level detail.
  5. Add the quote source, date and assumptions to the relevant row.
  6. Review formula columns, unpriced lines and totals before issue.

What the formulas calculate

The rate build-up uses the following structure:

Direct cost = material + labour + plant + subcontract + other direct cost
Unit cost = direct cost + material waste allowance + overhead allowance
Tender rate = unit cost + markup allowance

The BOQ Pricing sheet multiplies quantity by tender rate to calculate the line amount. Formula cells are shaded so they are easy to distinguish from inputs.

When a spreadsheet stops being enough

A workbook works well when one estimator owns a controlled version. It becomes harder to manage when several people update copies, supplier quotes change, or the priced BOQ needs to feed procurement and project controls.

At that point, a shared BOQ pricing workspace can keep the source, extracted lines, rate build-ups and handoff to procurement connected.

Scope and methodology

This guide explains a general construction estimating workflow for UAE contractors. Terminology, measurement rules and contract treatment vary by project. It does not provide legal, tax or contract advice, and it does not publish market rates.